Contract

DEWA OHL 4222000025, RFX  2122000124 : Installation of 11 KV Overhead on Wooden Poles & Dismantling & recovery of existing 33KV/ 11KV overhead lines.

  • Contract: Dubai Electricity & Water Authority (DEWA)
  • Client: Dubai Electricity & Water Authority (DEWA)
  • Main Contractor: EPS Electric Power Synergies LLC
  • Consultant: NOT APPLICABLE

Brief Scope of Work:

  • Site survey for Condition assessment, route markings and making of drawings.
  • Installation, testing and commissioning of Wooden & Tower poles.
  • Complete Testing & Commissioning of OHL up to 33 kV.
  • Refurbishment and maintenance of existing overhead lines up to 33 kV.
  • Removal & recovery of overhead line 33KV/11kV wooden pole foundations/steel structure along with complete accessories and return to DEWA scrap yard.
  • Transport to site 11 KV overhead line with poles crossarms (Including earth wire components and other hardware) insulators, pre-cast concrete foundations and assemble the poles along with accessories.
  • Making of OHL in mountain terrains as per specifications.
  • Make temporary or permanent access for new line construction.
  • Foundation design, construction and management
  • Conductor tension stringing.
  • Refurbishment and maintenance of existing overhead lines.
  • Make temporary or permanent access for new line construction.
  • Foundation design, construction and management